ACTION LIVING CONSTRUCTION PROGRESS: MAY 2024

MACCA | Screenshot 2025 04 04 at 3.32.21 p. m

When the ground is prepared, the real construction begins.

May marked a symbolic and engineering closing: the completion of the 100% earthwork. A process that often goes unnoticed, but which is decisive. Boxing, ground shaping, perimeter enclosures. Everything ready. Everything firm. Everything ready to start lifting.

With 13 of the 15 foundation piles already poured, the technical progress of the project exceeds 80% at this stage. And while the last two piles are being prepared for pouring, there is already talk of beams, columns and column starts. The language changes. From preliminary to structural. From the subway to the visible.

In parallel, the falsework for the slab on level -1, where the project's technical tanks will be located, has been installed. This is a key intervention that initiates a construction sequence of greater rhythm and visibility.

This is not just another step. It is the step that changes everything.

Action Living, the first fitness lifestyle hotel in the country, is no longer a rendering but a structure. A model that responds to a real market need, with millimetric technical execution and an approach that prioritizes profitability and experience.

To our investors: thank you for your trust. To the curious onlookers on the outside: this has already begun, and it's for real.

-

MACCA Team
Action Living Developers